by Janine | Dec 14, 2021 | Project Timeline
There will be multi-way traffic signals on the A58 Wetherby Road (at the junction of Redhall Lane) from 15/12/21 to 22/12/21 between the hours of 9.30am and 3.30pm Monday to Friday. This is to enable construction works as part of the East Leeds Orbital Road. We...
by Janine | Dec 3, 2021 | Project Timeline
There will be 2 way traffic signals on Skeltons Lane from 06/12/21 to 04/02/22 between the hours of 7.00am and 6.00pm Monday to Friday. This is to enable the installation of lighting columns and finishing works as part of the East Leeds Orbital Road. The traffic...
by Michelle Wathen | Dec 1, 2021 | Project Timeline
The temporary traffic lights on Leeds Road will need to be in place for a further three weeks (Monday to Friday 07:00 to 18:00). Delays in delivery of materials and some additional works added into the scope have meant we have had to increase the length of time the...