On the A6120 works has continued on the central island along with commencement of the new carriage way widenings on the north and south side of the central reservation to the east. These areas will be surfaced in the next few weeks.  Works are now progressing on the 4 verges of the A6120/A61 roundabout with drainage and new footpath construction.  At Scott Hall roundabout extensive works are ongoing exposing and protecting the existing services located within the road construction.  BT, Northern Power Grid and Northern Gas networks have continued with their diversion works which are progressing well.