Photo

A6120 East and West bound the construction of the new footpath/cycleway has continued with the surface water drainage now complete. Working with Leeds Parks and Countryside the underground tree architecture has been installed ready for tree planting later in the year. BT, Northern Power Grid and Northern Gas networks have continued their diversion works which will be completed in the next month facilitating the completion of the carriageway widenings.