On the A6120 East and West bound the construction of the new carriageway, footpath/cycleway has continued along with the surface water drainage. Leeds Parks and Countryside have commenced the installation of the underground tree architecture ready for planting later in the year. BT, Northern Power Grid and Northern Gas networks have commenced their diversion works which will, when completed, facilitate the completion of the carriageway widening.
To see the Phase 1A scheme drawing click here.